← All case stories

Case stories · Methods

Two cities, one creek, one price tag

Two cities, a conservation authority, and a botanical garden costed one watershed together. Replacing its stormwater services with engineered works would cost more than $2 billion, one time.

Where
Hamilton and Burlington, Ontario
Barrier
Methods
Trigger
A watershed shared by two cities, with flood and erosion risk rising as the climate changes
Tool
Replacement cost valuation at watershed scale, done jointly
Asset type
Swamps, marshes, forests, and open water in the Grindstone Creek watershed
Who did the work
The Natural Assets Initiative with the Cities of Hamilton and Burlington, Conservation Halton, and Royal Botanical Gardens, supported by the Greenbelt Foundation
The number
More than $2 billion in engineered replacements for stormwater services alone (one-time, excluding operations); about $34 million a year in co-benefits

Why Hamilton and Burlington started

Grindstone Creek rises in Hamilton and flows through Waterdown and Burlington into Hamilton Harbour at the Royal Botanical Gardens. The partners wanted to manage stormwater across the shared watershed as flood and erosion risk rise with the changing climate.

What Hamilton and Burlington did

The partners costed the whole watershed as one system. Replacing its stormwater services with engineered works would cost more than $2 billion, one time, before operating costs. They valued co-benefits such as erosion control, recreation, and habitat at about $34 million a year.

What it means for you

The method is the one Pelham later used. What's different is the partnership: one analysis shared by two councils, a conservation authority, and Royal Botanical Gardens. If a creek or wetland you manage crosses into a neighbouring municipality, you can cost it jointly with that municipality and your conservation authority.

Where it stands

The partners published the final report in late 2022, which the Natural Assets Initiative describes as the first project of its kind in Ontario. As of November 2026 Conservation Halton is updating the Grindstone Creek watershed management plan, due by 2027.