Let your parks flood on purpose and skip the bigger sewer

After a 2011 cloudburst, Copenhagen chose streets and parks that hold stormwater, with targeted pipes, over a bigger sewer system, because it cost less.

Where
Copenhagen, Denmark
Trigger
A cloudburst on 2 July 2011 that flooded the city and led to DKK 6.2 billion in insurance payouts
Tool
The Cloudburst Management Plan, which compared a bigger sewer system with a combined surface-and-pipe approach
Asset type
Streets, parks, and waterways redesigned to hold and route stormwater
Who did the work
The city and its water utility
The number
About DKK 11 billion for the combined approach, against DKK 20 billion for a bigger sewer system, both costs to society over 100 years; about 300 surface projects over 20 years; a projected net benefit of about DKK 5 billion over 100 years compared with doing nothing

Why Copenhagen started

On 2 July 2011 a storm dropped 135 millimetres of rain on Copenhagen in a single day, far more than the sewers were built for. Basements and roads flooded, and water came within centimetres of Rigshospitalet's emergency generators. Insurance payouts came to DKK 6.2 billion, Denmark's costliest natural disaster since 1999.

What Copenhagen did

The city chose a combined approach in its Cloudburst Management Plan of 2012. In 2013 and 2014 it worked out solutions for each of its seven catchments, about 300 surface projects over 20 years. In November 2014 it compared the two citywide options over 100 years: a bigger sewer system would cost society about DKK 20 billion, and redesigning streets, parks, and waterways to hold and route the water, with targeted cloudburst pipes, about DKK 11 billion.

What it means for you

Price both options for the same job and set the two numbers side by side, the way Copenhagen put DKK 11 billion beside DKK 20 billion. Where the green option comes in cheaper, that comparison is the argument. The city's own economics put the combined approach about DKK 5 billion ahead of doing nothing over a century.

Where it stands

Council adopted the plan in 2012, building on the climate adaptation plan it adopted in 2011. Tåsinge Plads opened in 2014 as the city's first climate-adapted square.

Where to go next

Step 5 of Your plan covers taking the plan to council and its ten-year financial strategy. The glossary's staff report entry says what a report on a natural asset should cover.