Your planners already have names for these assets. Use them

Markham listed its natural assets under the Ecological Land Classification names its natural heritage planners already used, and added them to its 2024 asset management plan as one category with a one-time replacement cost of $169.5 million.

Where
City of Markham, Ontario
Barrier
Methods
Trigger
In 2021 the city's natural areas were described in different terms: "natural features" in some planning documents, land cover types in one inventory, vegetation communities in another, and no woodlands or wetlands at all in the asset management plan
Tool
One classification, Ontario's Ecological Land Classification system, for both the natural heritage inventory and the asset register, plus definitions of how a natural asset fails
Asset type
Woodlands, wetlands, meadows, open water, hedgerows, beaches and bluffs
Who did the work
Natural heritage planning staff with Sustainability & Asset Management, Parks operations, Engineering, and Environmental Services, and a consultant team led by Green Analytics
The number
$169.5 million, the one-time cost to re-create the woodlands, meadows, wetlands, and hedgerows among the 986 hectares the city owns (open water isn't costed); their services valued at $60 to $62 million a year

Why Markham started

Markham is in York Region and partly in the Greenbelt, and about a fifth of the city, 4,100 hectares, is natural vegetation or water. In 2021 the city had two new inventories of that land, and they described it differently. The Natural Assets Initiative inventory treated each continuous area of one land cover type as an asset and counted 4,793 of them across 9,155 hectares, most of it farmland. Its authors noted that some city planning documents said "natural features" where they said "natural assets." The city's natural heritage inventory mapped vegetation communities using Ecological Land Classification. The asset management plan at the time included stormwater facilities, street trees, and parkland, but no woodlands, wetlands, or meadows.

What Markham did

A consultant team led by Green Analytics finished the Natural Assets Inventory and Evaluation Study in 2022, summarized in a 2024 staff report, with staff from planning, asset management, parks operations, engineering, and environmental services involved. The study counted woodlands, meadows, wetlands, and open water as natural assets, 4,108 hectares in all, 986 of them owned by the city. In the city's 2025 asset management plan, staff list each type under its Ecological Land Classification name, such as deciduous forest or meadow marsh, beside a one-time replacement cost per hectare carried over from the 2022 study: $173,847 for deciduous forest and $224,816 for meadow marsh. Under the plan, a natural asset can fail in three ways. Functional failure is when it stops doing its job, as when invasive species degrade it. Capacity failure is when it still works but can't keep up, as when rain exceeds what a forest can absorb. Service failure is when it delivers less, as when compacted forest soil lets less water soak in.

What it means for you

If your planners already map vegetation with Ecological Land Classification, you can use the same community names as the asset types in your register, so ecologists and asset managers work from one list. Before you compare inventories, check what each one counts: Markham's 2021 inventory included farmland and its 2022 study did not, and their totals were 9,155 and 4,108 hectares. You can also check your categories against CSA W218:23, the national standard for natural asset inventories.

Where it stands

Natural assets appear as their own category in Markham's 2025 asset management plan, which staff presented to General Committee on June 17, 2025, at $170 million to replace, about 1 per cent of the city's portfolio. The city's current management of them costs an average of $912,913 a year in capital and staff time, $504,010 of it for forest restoration. Stakeholders consulted for the plan raised invasive species, erosion from runoff off paved surfaces, and the money needed to keep the natural asset register current.

Where to go next

Each step of Your plan names a method and a free resource for it, many of them from the Natural Assets Initiative's 'Nature is Infrastructure' (2024).