Get everyone who holds the data at one table on day one
Oshawa valued the stormwater work of 7 kilometres of Oshawa Creek at $18.9 million by putting the conservation authority, which had the watershed plan and the hydrology model, in the room from the first meeting.
- Where
- City of Oshawa, Ontario
- Barrier
- Know-how
- Trigger
- The city wanted to know how the creek and its banks south of downtown were handling stormwater and erosion, and how to manage them so it wouldn't need more engineered works
- Tool
- A Municipal Natural Assets Initiative project: hydrologic modelling of the creek corridor and a condition summary drawn from existing watershed studies, with scenarios for restoration and low impact development at the sewer outfalls
- Asset type
- The southern 7 kilometres of Oshawa Creek, its riparian area, and its floodplain, between Adelaide Avenue West and the harbour
- Who did the work
- City parks, public works, engineering, and asset management staff; Central Lake Ontario Conservation Authority; the Municipal Natural Assets Initiative (now the Natural Assets Initiative); a University of Toronto civil engineering graduate student who ran the modelling
- The number
- $18.9 million for the stormwater conveyance the 7-kilometre reach provides, excluding the floodplain; $392 million to $414 million for the same 7-kilometre reach with its floodplain land, assuming greenfield construction; 41 outfalls draining about 450 hectares
Why Oshawa started
Oshawa Creek runs about 50 kilometres to Lake Ontario. Its last 7 kilometres run south of downtown, where 41 storm sewer outfalls drain roughly 450 hectares of homes and businesses built without the stormwater controls of newer development. The city owns a large part of the riparian land and manages most of the floodplain as parks. The creek's condition, though, lived in the conservation authority's files: Central Lake Ontario Conservation held the hydrology and hydraulics model, the floodplain mapping, and the 2013 watershed plan with its targets, including 30 per cent natural cover. The city's project report notes the new provincial regulation had just told municipalities to treat green infrastructure as infrastructure.
What Oshawa did
The project's first session, on May 29, 2018, had parks and public works, engineering and asset management staff, the conservation authority, the TeachingCity initiative, and local universities at the same table, and its job was to settle which assets to study, what data existed and who held it, and which skills were needed. The conservation authority supplied the model and the watershed plan; the city supplied the land, the outfalls, and the erosion problem; a University of Toronto graduate student did the modelling. The February 2020 report values the reach's stormwater conveyance at $18.9 million, and the reach with its floodplain land at $392 million to $414 million, before any co-benefits. It also records two gaps: the city could not supply operations and maintenance data, so no lifecycle cost comparison was possible, and the operations and maintenance plans were not completed for want of time and capacity.
What it means for you
Settle at the first meeting who has what. The conservation authority usually has the watershed plan, the floodplain mapping, and the model. The municipality owns the land and the outfalls and keeps the maintenance records, if it keeps any. Bring both sides, and bring the maintenance data, or the valuation stops short of a lifecycle comparison.
Where it stands
The report identifies and models preventative erosion measures on city-owned riparian land and low impact development at the outfalls, with the aim of improving the creek so that more engineered works aren't needed as development continues upstream. The report says the measures would work best upstream of the reach, and that many outfalls may not have room for them. As of November 2026, whether any were built is not published. The valuation covers stormwater only; flood storage, habitat, shade, and the corridor's value to priority neighbourhoods are named but not priced.
Where to go next
Your conservation authority may be able to do part of the work under an agreement. For training, look at the Natural Assets Initiative's Roadmap Program and Asset Management Ontario. All three are on Core organizations.
Sources
- Municipal Natural Assets Initiative, City of Oshawa: Oshawa Creek natural asset management project (February 2020)
- Natural Assets Initiative: City of Oshawa
Project team: City of Oshawa staff Michelle Whitbread, Patrick Lee, Harshad Patel, and Lucy Lovric; Lucy Benham and Perry Sisson of Central Lake Ontario Conservation; Haruna Monri-Fung and Bryan Karney of the University of Toronto.
Your aquifer can do a water plant’s job for $30K a year
British Columbia
How Gibsons budgets for its aquifer
Priorities · MoneyThe woods and wetlands are already handling $585 million worth of stormwater
Ontario
How Pelham priced what it would cost to replace them
Council supportTwo cities, one creek, one price tag
Ontario
How Hamilton and Burlington valued a shared watershed
Methods